1
|
Placemaking/Sitting place at Ridge.
|
Rs. 0.25
|
|
|
2
|
Refurbication of fountain/ site development near Takka Bench.
|
Rs. 0.43
|
|
|
3
|
Natural spring opposite Hotel Marina.
|
Rs. 0.43
|
|
|
4
|
Establishment of Smart open gym equipment at Police Line Kaithu.
|
Rs. 0.04
|
|
|
5
|
Development of Book Café at Chotta Shimla.
|
Rs. 0.65
|
|
|
6
|
Installation of E-toilets at important public places.
|
Rs. 0.66
|
|
|
7
|
SubziMandi (pocket-1 temporary shads-32 shops.)
|
Rs. 0.57
|
|
|
8
|
c/o 32 Nos. Temporary shops over existing slab of parking near lift Shimla including internal electrical installation for rehabilitation of shops.
|
Rs. 0.81
|
|
|
9
|
Road sweeping machine- 3.3 cum capacity.
|
Rs. 2.55
|
|
|
10
|
Road sweeping machine- 6.2 cum capacity.
|
Rs. 3.35
|
|
|
11
|
Knollswood turn widening of path at valley side.
|
Rs. 1.23
|
|
|
12
|
C/I on circular road in Shimla town.
|
Rs. 1.14
|
|
|
13
|
Construction/Improvement on circular road in Shimla town.
|
Rs. 1.01
|
|
|
14
|
Construction/Improvement on circular road in Shimla town.
|
Rs. 0.97
|
|
|
15
|
Widening & Improvement of Shimla Circular Road near Bemloe Shimla.
|
Rs. 2.19
|
|
|
16
|
Widening & Improvement of Shimla Circular Road near C.P.W.D at Nigam Vihar.
|
Rs. 1.54
|
|
|
17
|
C/I on circular road Shimla town.
|
Rs. 0.12
|
|
|
18
|
Improvement/widening in the area of Old Barrier near existing shops.
|
Rs. 2.88
|
|
|
19
|
C/I on circular road in Shimla town (near Cecil garrage)
|
Rs. 0.94
|
|
|
20
|
Improvement of junctions at Dhalli Chowk.
|
Rs. 1.34
|
|
|
21
|
C/I on circular road in Shimla town.
|
Rs. 1.10
|
|
|
22
|
Access from existing pedestrian path upto campus/ ground of Auckland
|
Rs. 0.15
|
|
|
23
|
Reconstruction and improvement of pedestrian path on Talland to Khalini.
|
Rs. 0.50
|
|
|
24
|
Widening/Imporvement of MRR via Chotta Shimla , near H.P. Seretariat
|
Rs. 0.46
|
|
|
25
|
C/o cycle stand & pedestrian path at HP secretariat Chotta Shimla
|
Rs. 0.24
|
|
|
26
|
Construction of footpath at Navbhar, St. Bedes College.
|
Rs. 0.47
|
|
|
27
|
Reconstruction of pedestrian path between Kali Dhank
|
Rs. 1.21
|
|
|
28
|
Improvement different stretches from Sadbhavana Chowk to Kasumpti.
|
Rs. 2.44
|
|
|
29
|
C/I on circular road in Shimla town.
|
Rs. 2.69
|
|
|
30
|
C/I on circular road in Shimla town.
|
Rs. 1.74
|
|
|
31
|
Installation of lift at Metropole parking.
|
Rs. 1.07
|
|
|
32
|
Installation of solar panels including net metering.
|
Rs. 5.83
|
|
|
33
|
Refurbishment of Padam Dev Complex.
|
Rs. 0.56
|
|
|
34
|
Provision of vending area at Vikas Nagar.
|
Rs. 0.52
|
|
|
35
|
Construction of Vending Zone Complex for street vendors near Subji Mandi Ground Shimla
|
Rs. 2.00
|
|
|
36
|
Fixing Murals in wall in front of Police Station East Chotta Shimla.
|
Rs. 0.25
|
|
|
37
|
Construction of additional parking near Jiwanoo Colony, Panthaghati.
|
Rs. 0.95
|
|
|
38
|
Construction of Commercial Complex at Kasumpti Shimla.
|
Rs. 1.60
|
|
|
39
|
Construction of Smart Bus-Stop at Kennedy Chowk near Vidhan Sabha.
|
Rs. 0.53
|
|
|
40
|
Rani-Jhansi Park at Ridge.
|
Rs. 0.51
|
|
|
41
|
Park at Gol Pahadi near Annadale.
|
Rs. 1.09
|
|
|
42
|
Face lifting of existing parks Below Ashiana at Ridge.
|
Rs. 0.26
|
|
|
43
|
Development of parks and open spaces in different wards.
|
Rs. 2.09
|
|
|
44
|
Reconstruction and improvement of pedestrian path on KSC road.
|
Rs. 0.90
|
|
|
45
|
Reconstruction of W. beam Railings. (RDs 145/100 to 149/000. )
|
Rs. 1.30
|
|
|
46
|
Improvement of pedestrian path on Circular road. (RD 152/500 to 148/640.)
|
Rs. 3.83
|
|
|
47
|
Improvement of pedestrian path and W. metal beam crash barrier railings on MRR via Chotta Shimla.
|
Rs. 1.85
|
|
|
48
|
Construction of footpath, covered drain, paver block and safety railings on KSC/ MRR road.
|
Rs. 1.65
|
|
|
49
|
Construction of Smart pedestrian path.
|
Rs. 0.33
|
|
|
50
|
Providing drain etc. from Dhalli tunnel to Mashobra junction 153/180 to 155/00
|
Rs. 2.14
|
|
|
51
|
C/O addl. Pedestrian path, P/F W. beam metal crash barriers railings.
|
Rs. 1.95
|
|
|
52
|
Relocation of Kamna Devi Temple Road .
|
Rs. 4.94
|
|
|
53
|
Reconstruction of Shopping Complex.
|
Rs. 2.38
|
|
|
54
|
Improvement of Y-junction at Dhalli Tunnel.
|
Rs. 1.58
|
|
|
55
|
Providing drain etc. from Dhalli tunnel to Mashobra 153/180 to 153/765
|
Rs. 2.00
|
|
|
56
|
Providing drain etc. from Dhalli tunnel to Mashobra junction. RD 153/725 to 153/785 and 154/310 to 154/361.
|
Rs. 1.69
|
|
|
57
|
Providing drain etc. from Dhalli tunnel to Mashobra junction- 153/765 to 154/500.
|
Rs. 3.05
|
|
|
58
|
Provision of Breast wall and other protection work.
|
Rs. 2.09
|
|
|
59
|
C/I on circular road in Shimla town. (RDs 150/290 to 150/380)
|
Rs. 1.85
|
|
|
60
|
Widening of Road from MLA crossing to Tawi more.
|
Rs. 0.93
|
|
|
61
|
Metalling/Tarring in various locations.
|
Rs. 1.35
|
|
|
62
|
Construction of Breast wall and Protection work between (RD 149/520 to 149/570., Total length = 50 mtrs). Location- Below HHH.
|
Rs. 0.75
|
|
|
63
|
Improvement of Shimla Mandi Road portion RDs 6/0 to 11/0.
|
Rs. 3.00
|
|
|
64
|
Widening of circular road and Protection work near Subzi Mandi
|
Rs. 0.68
|
|
|
65
|
Construction/Improvement road from Brock Hurst to Vikasnagar.
|
Rs. 1.22
|
|
|
66
|
Widening of road ahead of Kasumpti Bazar towards Panthaghatti.
|
Rs. 0.83
|
|
|
67
|
Construction/Improvement on circular road in Shimla town (near Ranjan Hotel)
|
Rs. 1.32
|
|
|
68
|
Improvement of junction at Bemloe Chowk .
|
Rs. 1.22
|
|
|
69
|
Development of smart parking's in wards as per availability of land. Phase 1
|
Rs. 3.52
|
|
|
70
|
Construction of parking at Circuit house Willy park from cart road near RTO.
|
Rs. 0.59
|
|
|
71
|
Construction of parking near Raj Bhawan HPPWD Sub-Division.
|
Rs. 0.90
|
|
|
72
|
Construction of Off street parking near Sankat Mochan.
|
Rs. 4.50
|
|
|
73
|
Development of Book Café at Chaura Maidan.
|
Rs. 0.94
|
|
|
74
|
Refurbishment of shops at SubziMandi (pocket-1) 65 shops and 13 stores.
|
Rs. 2.07
|
|
|
75
|
Refurbishment of shops at SubziMandi (Pocket-2) 28 shops and 3 stores.
|
Rs. 1.03
|
|
|
76
|
Refurbishment of shops at Lower Bazar (39 No. shops and 15 No. basements)
|
Rs. 3.64
|
|
|
77
|
Refurbishment of shops at Ram Bazar (40 shops)
|
Rs. 1.85
|
|
|
78
|
Refurbishment of 4 Residential Blocks (36 flats) at Ghora Line Krishna Nagar.
|
Rs. 4.94
|
|
|
79
|
Unsafe/dilapidated building at Near Tibetan School, Chotta Shimla.
|
Rs. 1.49
|
|
|
80
|
Unsafe/dilapidated building at Ghora Hospital, Cart road, Shimla.
|
Rs. 1.25
|
|
|
81
|
Installation of escalators at Jakhu temple.
|
Rs. 7.77
|
|
|
82
|
Installation of lift at MC Old Bakery Building.
|
Rs. 1.72
|
|
|
83
|
Foot over Bridge at Vikas Nagar. Phase 1
|
Rs. 2.97
|
|
|
84
|
Foot Over Bridge at Chalaunthi Chowk.
|
Rs. 5.12
|
|
|
85
|
Foot Bridge near Kennedy Chowk connecting to Vidhan Sabha Shimla.
|
Rs. 0.36
|
|
|
86
|
Construction of covered footpath along Sanjauli-IGMC road.
|
Rs. 23.33
|
|
|
87
|
Construction of Subway at Himland Hotel on MRR via Chotta Shimla.
|
Rs. 0.70
|
|
|
88
|
Smart bus stop at Talland- valley side. (Type-B)(RDs 151/095)
|
Rs. 0.99
|
|
|
89
|
Construction of Rain Shelter at Vikasnagar bus stop and pedestrian path.
|
Rs. 0.22
|
|
|
90
|
Smart bus stop at different locations in Shimla City.
|
Rs. 2.34
|
|
|
91
|
Booth for traffic police & LED traffic lights, high mast lights and signages at different locations.
|
Rs. 3.55
|
|
|
92
|
Initiatives for Govt. High School Krishna Nagar.
|
Rs. 5.31
|
|
|
93
|
Coverage of Shimla city under CCTV surveillance.
|
Rs. 0.50
|
|
|
94
|
Implementation of Smart Metering in Shimla Town.
|
Rs. 10.00
|
|
|
95
|
Construction of tunnel parallel to Dhalli tunnel.
|
Rs. 69.70
|
|
|
96
|
Replacement of Old fire hydrants at various locations in Shimla City.
|
Rs. 0.34
|
|
|
97
|
Covered Garbage vehicles (34Nos.-5 cum capacity)
|
Rs. 4.59
|
|
|
98
|
Regarding procurement of 4 Nos.(14 cum capacity).
|
Rs. 1.33
|
|
|
99
|
Improvement of approach road from Mall road to Peterhoff Shimla
|
Rs. 1.86
|
|
|
100
|
Widening & Improvement of Sanjauli Bazar Chowk.
|
Rs. 5.65
|
|
|
101
|
Development of parking –cum-commercial complex near Bangala Colony, Totu on MC land.
|
Rs. 6.50
|
|
|
102
|
Beautification of Secretariat building with vertical garden at various entrances.
|
Rs. 0.15
|
|
|
103
|
Widening/Improvement of MRR Lakkar bazar road Victory Tunnel to Sanjauli at RD 147/825 to 153/075 (SH: PCC Retaining Wall at RD 149/210 to 149/270) Below PNT Colony under Shimla Smart City.
|
Rs. 0.58
|
|
|
104
|
C/o Parking at Tutikandi under Shimla Smart City project (SH: Construction of Building Portion) under Shimla Smart City.
|
Rs. 0.65
|
|
|
105
|
Widening/Improvement of MRR via Lakkar Bazar from Victory Tunnel to Sanjauli (Near Hotel Royale Retreat) Km. 147/825 to 153/075 (SH: C/o PCC B/Wall at RD 147/920 to 147/945, 147/977 to 147/990 and C/o RCC projected path partly covered with Roof & P/F Railing at RD. 147/890 to 148/040)
|
Rs. 1.75
|
|
|
106
|
Improvement and Widening of Chotta Shimla to Panthaghatti road (SH: Fixing of Road side Gratting in Chotta Shimla to Panthaghati road at RD. 0/145 to 0/875)
|
Rs. 0.30
|
|
|
107
|
Providing and installation U Shape, L-Shape gantries, I Shape signage board & sign board at various locations in Shimla town.
|
Rs. 0.73
|
|
|
108
|
Construction of Toilets near lift Mall road (SH: Construction of Building portion with Civil work and water supply & Saintary Installation work etc) under Shimla Smart City.
|
Rs. 0.17
|
|
|
109
|
Construction of Footpath from Raj Bhawan to Navbahar chowk on Circular road Shimla Km. 152/500 to 154/375 under Shimla Smart City mission.
|
Rs. 1.89
|
|
|
110
|
Improvement and Widening of Chotta Shimla Kaumpti Panthaghati road(SH: Shifting of existing boundary wall and re-construction of boundary wall on road from Chotta Shimla to Kasumpti(Near Tibetian School) in Shimla town.
|
Rs. 0.27
|
|
|
111
|
Widening/Improvement of MRR via Lakkar Bazar km. 147/825 to 153/075 (SH: C/o widening of road at RD 149/500 to 149/560, v-shape drain between km. 147/900 to 150/10 and c/o raised foot path between km. 149/420 to 149/600) near khadio Gram Udyog/ Ice Skating Rink under Shimla Smart City.
|
Rs. 1.75
|
|
|
112
|
Widening/Improvement of MRR via Lakkar Bazar k. 147/825 to 153/075 (SH: C/o B/wall at RD 149/0 to 149/015, cutting from RD 151/150 to 151/315, C/o R/wall Rd 151/585 to 151/630, C/o B/wall at RD 151/720 to 152/735), C/o R/wall RD 151/810 to 151/820 i/c railing, C/o B/wall 15/075 to 152/120, R/wall 15
|
Rs. 1.54
|
|
|
113
|
Widening of Improvement of MRR via Lakkar Bazar from Victory Tunnel to Sanjauli KM. 147/825 to 153/075 (SH: C/o PCC, R/wall at RD 148/720 to148/775 and Toe wall at RD 148/780 to 148/870)
|
Rs. 0.81
|
|
|
114
|
Widening/ Improvement from Kasumpti to Mehli (GAD Colony) Km.0/00 to 0/550 (SH: Widening and C/O Pedestrian path from RD. 0/196 to 0/485) under Shimla Smart City mission.
|
Rs. 2.57
|
|
|
115
|
Improvement of junction Auckland Tunnel on MRR via Lakkar Bazar (SH: Widening of Chowk, C/o retaining wall & breast wall and C/o Rain Shelter (near proposed subway)Near Auckland) under Shimla Smart City
|
Rs. 0.80
|
|
|
116
|
Construction of Subway at MRR via RKMV Lakkar Bazar near Auckland Tunnel between RD 150/150 to 150/65 under Shimla Smart City.
|
Rs. 0.88
|
|
|
117
|
Construction of open of Stadium at Sanjauli near S.P.M. School. (SH: Development works for ground, fencing, Stage, railings and sitting area) under Shimla Smart City.
|
Rs. 1.78
|
|
|
118
|
Widening/Improvement of Chotta Shimla Kasumpti Road (Partially dismantling/ Reconstruction of temple and dismantling/reconstruction of shops at Chotta Shimla)
|
Rs. 0.90
|
|
|
119
|
Improvement and widening of Navbhar Bhumia road Km.0/0 to 2/150 Kms.(SH: Formation cutting, passing places, R/Walls, C.D. Work, GSB, WBM-II, WBM-III, Tarring work, side drain parapets and C.C. pavement.
|
Rs. 1.96
|
|
|
120
|
Constructions of alternate road from Rajhana to Shoghi bye pass near Sewerage Treatment plant.
|
Rs. 3.00
|
|
|
121
|
Procurement of 4 Nos. of ROBOT machines i.e. Bobcat Make Skid Steer Loader with snow blower attachment through HPPWD Mechanical wing.(Two for MC Shimla and two for HPPWD Division I)
|
Rs. 2.00
|
|
|
122
|
C/o Parking and Widening of Navbahar to Holy Lodge Road at RD 1/990 to 2/085
|
Rs. 2.91
|
|
|
123
|
Widening of Exit turning point of Armasdale building from mall road side at H.P. Secretariat Chotta Shimla (SH:- Construction of Retaining wall at RD’s 0/010.5 to 0/0.24.70)
|
Rs. 0.14
|
|
|
124
|
Widening of turning point of Cart road to mall road at Chotta Shimla (SH:- cutting work a/w construction of 32.00 mtrs C.C Breast wall etc.
|
Rs. 0.23
|
|
|
125
|
Construction of Retaining wall near exit road of Armsdale building below stand for transformer at HP Secretariat Chotta Shimla.
|
Rs. 0.03
|
|
|
126
|
C/o parking near Metropole under Smart City Mission
|
Rs. 1.01
|
|
|
127
|
Widening of road from HP High Court to Chalet day Chowk under Shimla Smart City Project.
|
Rs. 0.70
|
|
|
128
|
Construction of parking and extension of Tennis Court at Site BTC Block at Nabha Estate Shimla.
|
Rs. 2.72
|
|
|
129
|
Beautification of retaining walls on various roads under Shimla Smart City Project.
|
Rs. 0.92
|
|
|
130
|
C/O Steel Footpath on Shimla By Pass road on NH-22 (new NH 05) at km 9/985 to 10/395 (SH :- C/O Steel footpath and providing and fixing interlocking Paver Block on Berms etc. (Against Smart City) from Vikasnagar to TCP office.
|
Rs. 1.41
|
|
|
131
|
C/O Steel Footpath on Shimla By pass on NH 22 (New NH 05) at km 1/505 to 1/660 (SH:-C/O Steel footpath and providing and fixing interlocking Paver block on Berms and construction of B/wall at RD 1/670 to 700 on Shimla by pass (Against Smart City) at Tutkandi.
|
Rs. 1.25
|
|
|
132
|
Construction of Book Café in Sector III, New Shimla.
|
Rs. 1.01
|
|
|
133
|
Construction of Foot over Bridge at Vikasnagar -Phase II & III.
|
Rs. 7.61
|
|
|
134
|
Construction of parking under Shimla Smart City Mission Phase III.
|
Rs. 2.69
|
|
|
135
|
C/O Steel Footpath on Shimla By Pass road on NH-22 (new NH 05) at km 6/436 to 7/360 (SH :- C/O Steel footpath and providing and fixing interlocking Paver Block on Berms etc. (Against Smart City) from Khalini to Mist Chamber.
|
Rs. 1.88
|
|
|
136
|
C/O Steel Footpath on Shimla By Pass road on NH-22 (new NH 05) at Km 12/500 to 13/000(SH :- C/O Steel footpath and providing and fixing interlocking Paver Block on Berms etc. (Against Smart City) from Mehli to Brahma Kumaris Ashram (Panthaghati).
|
Rs. 1.94
|
|
|
137
|
C/o Entry Gate on NH-88(new NH-205) on Kalka Shimla Wangtoo road near Chharabra at km 154/980 to 155/300 (Against Smart City)
|
Rs. 0.51
|
|
|
138
|
C/o Entry Gate on NH-88(new NH-205) on Kalka Shimla Wangtoo road near Taradevi at km 140/780 (Against Smart City)
|
Rs. 0.53
|
|
|
139
|
C/o Entry Gate on NH-88(new NH-205) on Kalka Shimla Wangtoo road near Totu between at km 2/645 to 2/700 (Against Smart City)
|
Rs. 0.51
|
|
|
140
|
C/O Steel Footpath on Shimla By Pass road on NH-22 (new NH 05) at Km 11/965 to 12/500 (SH :- C/O Steel footpath and providing and fixing interlocking Paver Block on Berms etc. (Against Smart City) from Panthaghati to Brahma Kumaris Ashram (Panthaghati).
|
Rs. 1.82
|
|
|
141
|
Improvement of Y-junction at Dhalli Tunnel- M/T on extended portion on Hill/ Valley side. RDs 153/180 to 155/045 and 24/180 to 24/250.
|
Rs. 0.63
|
|
|
142
|
C/O Steel Footpath on Shimla By pass road on NH-22 (new NH 05) at km 11/140 to 11/610 (SH:- C/O Steel footpath and providing and fixing interlocking Paver Block on Berms etc, (Against Smart City) from Panthaghati to Shiv Mandir.
|
Rs. 2.04
|
|
|
143
|
Refurbishment of 850 Numbers Solar Lights.
|
Rs. 2.11
|
|
|
144
|
C/O Steel Footpath on Shimla By Pass road on NH-22 (new NH 05) at km 9/440 to 9/985 (SH:-C/O Steel footpath and providing and fixing interlocking Paver Block on Berms etc. (Against Shimla City) at Vikasnagar near S.V.M School.
|
Rs. 2.12
|
|
|
145
|
C/O Steel Footpath on Shimla By Pass road on NH-22 (new NH 05) at km 10/400 to 11/140 (SH :- C/O Steel footpath and providing and fixing interlocking Paver Block on Berms etc. (Against Smart City) near TCP office to Shiv Mandir.
|
Rs. 2.10
|
|
|
146
|
Construction of Vending Zone at Dhalli Chowk near HPPWD office (Valley Side).(SH: C/o 15 units of vending zone size 2.4x1.80 mtr.) under Smart City Mission.
|
Rs. 0.41
|
|
|
147
|
Construction of Commercial Complex Part-II near Patwar Khana (Sh: Parking block at Kasumpti Shimla.)
|
Rs. 1.31
|
|
|
148
|
Elevated smart walkway from Chotta Shimla to Ayurvedic Hospital on Chotta Shimla - Kasumpti road.
|
Rs. 12.78
|
|
|
149
|
Installation/Construction of elevator/lift at middle Bazar Shimla accessible for 8 persons under Shimla Smart City.
|
Rs. 1.77
|
|
|
150
|
Balance work for Construction of Ground/Open Space near Primary School ward No. 7 Majiyath (SH: - Cutting work, C.C work & Steel work etc.)
|
Rs. 0.21
|
|
|
151
|
Development of open vacant space/food court in front of vending complex near Lift
|
Rs. 0.38
|
|
|
152
|
Construction of covered path from Keyman Qtr. To Jakhu Temple in Ward no. 16 (RD 0/0 to 0/300 mtr.) under “Shimla Smart City Mission”.
|
Rs. 2.03
|
|
|
153
|
Installation of New Toilets within MC Shimla under Shimla Smart City Mission.
|
Rs. 0.47
|
|
|
154
|
C/o parking alongside the road from Sanjauli to Dhingu Dhar in ward no. 22 Shanti Vihar, Phase-II.
|
Rs. 0.36
|
|
|
155
|
Development of smart parking's in wards as per availability of land Phase II.
|
Rs. 1.93
|
|
|
156
|
Construction of parking under”Shimla Smart City Mission” Phase IV (4 New parking’s proposed and additional amount for 8 parking)
|
Rs. 4.50
|
|
|
157
|
Construction of parking under”Shimla Smart City Mission” Phase V (24 New parking’s proposed)
|
Rs. 7.09
|
|
|
158
|
Construction of Parking under “Shimla Smart City Mission” Phase VI. 1. Near Kalibari Temple, Ruldubhata, 2. Himgiri Colony, Dhalli, 3. Jaswal House Boileaganj, 4.Corner House, MC Residence Ward no. 17
|
Rs. 2.00
|
|
|
159
|
High mast lights and Smart Street Lights in all 34 wards of MC Shimla • Proposed Smart Street Lights: 1000 approx. • Proposed High Mast Lights: 10 approx
|
Rs. 4.80
|
|
|
160
|
Construction of Senior Citizen Club, Community Centre and Children Reading Room Adjacent to Sanjauli Reservoir in Ward No. 19 (Sanjauli Chowk) under Shimla Smart Limited.
|
Rs. 2.10
|
|
|
161
|
Improvement/widening of Circular Road from starting Talland to CPRI Colony and providing footpath on valley side under Shimla Smart City.
|
Rs. 1.38
|
|
|
162
|
Providing footpath on Valley side of Circular Road from starting of B-4 Bunglow Bemloe to end of Block-4 Servant Qtrs Building Bemloe at Cart Road under Shimla Smart City
|
Rs. 1.31
|
|
|
163
|
Improvement/widening of Road starting from Tunnel 103 in front of SSB Training Centre to Tutikandi bye passes under Shimla Smart City.
|
Rs. 3.44
|
|
|
164
|
Footpath on valley side starting from Tunnel 103 in front of SSB Training Centre to Tutikandi bye passes under Shimla Smart City.
|
Rs. 2.73
|
|
|
165
|
Improvement/widening of Circular Road in front of SSB Training Centre under Shimla Smart City.
|
Rs. 1.78
|
|
|
166
|
Development of Park near Middle Land Bunglow on K.N.H. Hospital road
|
Rs. 0.55
|
|
|
167
|
Improvement/widening of circular Road from starting of B-4 Bunglow Bemloe to end of Block-4 servant Qtrs Building Bemloe upto HHH at Cart road under Shimla Smart City.
|
Rs. 3.06
|
|
|
168
|
Providing footpath on valley side starting from All India Radio to Labour Bureau office under Shimla Smart City.
|
Rs. 3.80
|
|
|
169
|
Providing footpath on valley side from starting of Advance study to All India Radio under Shimla Smart City.
|
Rs. 3.00
|
|
|
170
|
Improvement/ widening of Circular Road from Bemloe Chowk to Bye Pass Road under Shimla Smart City.
|
Rs. 4.47
|
|
|
171
|
Improvement/ widening and providing footpath on valley side starting from Cisel Hotel to NAAA(Kotshera College) under Shimla Smart City.
|
Rs. 3.69
|
|
|
172
|
Providing footpath on valley side starting from Bemloe Chowk to By Pass Road under Shimla Smart City.
|
Rs. 4.30
|
|
|
173
|
Restoration of road from National Highway to Lalapni, Construction & Repair retaining wall, providing parking facility and allied civil works at Lalpani Shimla.
|
Rs. 1.91
|
|
|
174
|
Widening of road including construction of Pedestrian from Perci Villa to Briror Villa along with NH under Shimla Smart city Projects.
|
Rs. 1.85
|
|
|
175
|
Refurbishment of toilets at Ridge and near Rotary Club
|
Rs. 1.03
|
|
|
176
|
Land acquisition as per requirement.
|
Rs. 1.41
|
|
|
177
|
Development of Pvt. Sector: C/O Single Room ACC 1 Unit Block No.4 (4 No. Flats) without parking SIKH LINE at Krishna Nagar Shimla including internal and external services.
|
Rs. 0.98
|
|
|
178
|
Traffic Equipment for Traffic Police in Shimla under Smart City Projects.
|
Rs. 0.60
|
|
|
179
|
Estimate for conversion of overhead conductor of 11 KV Kanlog with underground 3x 300 mm2 XLPE cable from 4 pole structure Lalpani to 3 way RMU under smart city project.
|
Rs. 0.95
|
|
|
180
|
Regarding installation of Grid connected Rooftop Solar Plants in Govt. residence in Shimla City under the Shimla Green/Solar City.
|
Rs. 2.90
|
|
|
181
|
Initiatives for Smart School-Development of 11 Govt. Sr. Sec. Schools as smart school for within MC Limits. 1. Boilaeuganj 2. Chotta Shimla 3. Khalini 4. Lakkar Bazar Shimla (Girls) 5. Lalpani Shimla (Boys) 6. Phagli 7 Portmore (Girls) 8. Sanjauli 9. Summer Hill 10. Totu 11. Tutikandi.
|
Rs. 1.76
|
|
|
182
|
Setting up of Integrated Command and Control Centre (ICCC) for Shimla Smart City.
|
Rs. 41.01
|
|
|
183
|
Consultancy Service for preparation of urban roads improvement plan alternate roads for Shimla Smart City.
|
Rs. 5.08
|
|
|
184
|
Development of Nature/Botanical/Eco Park Gaduag Beat of Totu Forest Block.
|
Rs. 0.51
|
|
|
185
|
Estimate for replacement of 3 phase LT line overhead bare Conductor with AB cable 3x185+50+185mm 2 cable at Krishana Nagar, Subzi Mandi &Ganj Road and surrounding area under Smart City Project in Electrical Section Subzi Mandi under ESD, HPSEBL, Ridge, Shimla-1.
|
Rs. 1.92
|
|
|
186
|
Development of Bus Stand, Transport Office, Workshop and Commercial Complex at Dhalli.
|
Rs. 12.00
|
|